Jan 23, 2023     Avionics and Electrical - (8.9 hours) Category: Avionics
Continued working on schematic and wiring spreadsheet. Completed first complete pass through all items on the spreadsheet and the schematic. Added switches and power and ground connections to the schematic and spreadsheet as needed. Still have some open questions to discuss with other builders, but the initial plan is documented. Next steps:
- quick review and cleanup to make the schematic easier to read and then print a copy and send to others for review (1/24)
- need to complete panel layout including switches to verify I have room for the parts in the current design or if I need to revise it to use fewer switches.
- need to complete determining wire size and type and shielding connections (future).
 